V
Vit
Hi All,
I'm a little confused from a request of my boss....
he want to assign the resources at the summary task level, when he is
plannig,
AND
record the time spent at the task level, when he is tracking....
maybe better with an example....
Drilling
Drilling Rock
Drilling Soft Rock
Drilling Sand
he would like to assing resources to the drilling phase
AND
track the time at the specific task...
in the planing phase it will be:
Drilling bob (70h), rob
(50h)
Drilling Rock
Drilling Soft Rock
Drilling Sand
in the tracking it will be:
Drilling bob (140h),
rob (100h)
Drilling Rock bob (30h), rob
(30h)
Drilling Soft Rock bob (20h), rob (15h)
Drilling Sand bob (20h), rob
(5h)
the problem is that at the end of the drilling phase, at the summary
level, I will have doubble... the summary + the precific tasks....
what is the best way to manage this situation????
in the planning phase, my boss dont want to insert the resources at
the task level, because he think that it is not easy to guess and plan
who will perform the job and haw much time it will take... instead, it
is easy to insert just at the summary level.....
thank all
cheers
Vit
I'm a little confused from a request of my boss....
he want to assign the resources at the summary task level, when he is
plannig,
AND
record the time spent at the task level, when he is tracking....
maybe better with an example....
Drilling
Drilling Rock
Drilling Soft Rock
Drilling Sand
he would like to assing resources to the drilling phase
AND
track the time at the specific task...
in the planing phase it will be:
Drilling bob (70h), rob
(50h)
Drilling Rock
Drilling Soft Rock
Drilling Sand
in the tracking it will be:
Drilling bob (140h),
rob (100h)
Drilling Rock bob (30h), rob
(30h)
Drilling Soft Rock bob (20h), rob (15h)
Drilling Sand bob (20h), rob
(5h)
the problem is that at the end of the drilling phase, at the summary
level, I will have doubble... the summary + the precific tasks....
what is the best way to manage this situation????
in the planning phase, my boss dont want to insert the resources at
the task level, because he think that it is not easy to guess and plan
who will perform the job and haw much time it will take... instead, it
is easy to insert just at the summary level.....
thank all
cheers
Vit