Hello Tariq,
The only item available for editing on the Project Summary report is
the font formatting, sorry. The information in the report showing
under Date, Duration, Work, and Costs is available through fields
that can be displayed in a custom table when viewing the Project
Summary task.
The count information (Task Status and Resource Status) would be
more difficult to present in a report in Project.
I hope this helps. Let us know how you get along.