SV in days

  • Thread starter Alexander Barvinsky
  • Start date
A

Alexander Barvinsky

Hi,
I can't find "SV in days" field in EV tables. Is it exist at all or I have
to calculate it manually?
Thank's

Alerxander Barvinsky
Director of Operations Department
 
K

Kevin W Flanagan

You can create a custom field and place a formula in it that will
automatically calculate SV for you.
 

Ask a Question