This speaks to a related issue. They start the task they day
they
pick them
up and put their initials and the date there, so it really is an
actual
start. perhaps i just let Project go off those and not worry
about
leveling
resources?
i think i'm finally getting it to change the task bar when i
change
the
calendar. i just deleted all my calendars and started over.
seems
to be
working now.
thanks
scott
:
Scott,
It doesn't sound as though you are using the Actual Start to
really
record when a resource actually starts only when the pick the
task
they wish to do. Can you pull the date information into a spare
date
field? Your resource leveling should also not be working
correctly
if
you've entered in Actual starts for tasks -- once a task has an
actual
start, it cannot be delayed by leveling.
If you are simply importing the data you note into the project,
then
changing the resource's base calendars to the 10hr day should be
changing the finish date of the tasks as each resource can get
his/her
work done in a shorter period of time as they are working more
hours
per day.
Try stepping through the process on a new project file. Create
one
task with 5 days duration starting Monday and ending Friday at
5:00
pm
and one resource assigned at 100% with 40 hours of work. If you
chage
the task calendar to the 10hr per day calendar the task duration
will
still say 5 days (40 working hours) but the finish date should
move
to
Friday at 8:00 am.
Julie
message
Here's the big picture:
Currently, resources select jobs (tasks) as they choose. They
use
Access to
put their initials by the task name. I've coded it so that
Access
runs a
macro and a few queries to get the info i want, and then
uploads
it
into
Project, which automatically reads it in (by merging) and
levels
the
resources. Until a task is selected by resource (as shown by
them
putting
their initials next to it in Access) the Resource Initials in
Project are
"Yes". At the time they put their initials into Access, they
also
put in the
current date, which gets uploaded to Actual Start. No tasks
are
linked.
Everything is automatic. So the project exists forever, and
the
tasks come
in and out as they are assigned to us and finished. It's just
that
at times
when we're slammed, i want to be able to go in, change to a 10
hour
workday,
and see if we can make some more deadlines on these individual
tasks.
does this help? i'm happy to clarify anything
thanks!
scott
:
Scott,
Are you trying to import actual work using Access or are you
trying
to
create a project file using tasks in access? Have you linked
the
tasks in Project? You should only be changing actual work if
the
task
has actually been started by the resource and you are
attempting
to
report tracking data.
If you are attempting to make the project finish earlier and
you
have
constrained all tasks with a SNET constraint, changing the
calendar
to
10 hour days won't accomplish what you want. A SNET
constraint
means
that the linked tasks will *not* move any earlier even if all
of
your
resources work 24 hours per day. Each individual task will
finish
earlier but you won't accomplish the goal -- speeding
progress
on
the
project.
I'd suggest keeping the data in Project and updating project
directly,
not attempting to import from Access. Without further
information
about why you are using Access and Project -- it's tough to
recommend
other options.
Julie
message
interesting. yeah, i'm importing Task Name, Deadline,
Resource
Initials,
Duration, Date1, and Actual Start. so that actual start
means
this
isn't
going to work?
In in the Gantt chart view, task calendars all say "none."
All the tasks have constraints of SNET.
It seems like there should be a way for this to work. I'm
only
constraining
when it starts, not when it finishes.
So where should i go from here?
thanks
scott
:
Hi Scott,
You haven't applied task calendars to every task have you?
If
you
add
the Task Calendar column to the table it should say "none"
not
the
name of *any* calendar.
When you import information from Access are you bringing
over
start
and finish dates? If so, you are likely constraining the
tasks.
Do any indicators show in the indicator column next to the
tasks?
Have you applied any actual data (actual start, actual
finish,
percent
complete etc) to the tasks? If tasks have any tracking
(actual)
data,
then changing the calendar will not change them.
Julie
message
So if i set Project->Project info to Standard, and then
Tools->Change Working
Time to 7am to 6pm for the standard calendar, then the
task
bars
go
till 6
pm, regardless what calendar i have the resource on.
but
if i
change Project
info to 10hourdays, it still uses the standard calendar.
this
thing
is just
constantly using the standard calendar.
importing: i have it automatically merging data from an
Access
table
using
an import map
i've stopped messing with Tools->option->calendar. it's
set
to
use
a
regular 8 hour day.
i think it can do exactly what i want it to; i'm just
having
trouble
getting
it to do it.
thanks Julie,
scott
:
Hi Scott,
My comments are inline
I hope this helps.
Julie
in
message
Julie, i'm not quite seeing what you are. I imported
tasks
using
an
8 hour
day, Standard calendar.
[Julie] How are you "importing tasks"? If you are
copying
and
pasting
tasks you may very well be picking up constraints by
copying
and
pasting dates. Why are you importing tasks into other
projects?
But if i just go to Tools > Options, Calendar and
change that 8 hours per day to 10 hours per day,
50hrs/week,
and
7am
to 6pm,
nothing shifts on the gantt chart.
[Julie] Nope, I didn't say anything about going to
Tools >
Options,
Calendar tab
. Please see FAQ #5 at:
http://project.mvps.org/faqs.htm
If i change the task info to 10hourdays,
the project info to 10hourdays, and the resource base
calendar
to
10hourdays,
and Tools->Options->calendar to 10hrs/day, and then
reimport,
still
nothing
changes.
[Julie] Did you create the 10hr day through Tools >
Change
working
time? Did you set *all* working days to 7:00 am to
6:00
pm?
Do
you
have resource assigned to the tasks? If you have
assigned