×
גיל
Hi good people..
Every time we open a specific project (Project Server 2007) we get "This
action may result in Actuals out of sync with.." message (the "Restrict
updates" option is
enabled). We go to tracking > sync with actuals, and save , but when we open
the
project again, we get the sync message again, before we even did anything at
all.
How can we sync back with actual from PWA..?
Also, Project wrongly spreaded hammock task's actual work, entered by user
in PWA, to something like 0.18h for every day of the next few weeks, so we
have changed the hammock task to fixed units and deselect effort driven, but
how do I recover the original (pre-spread) actual work values? can the
hammock task be the cause of the unfixable out-of sync state?
Thanks for any attempt to help..
Gil.
Every time we open a specific project (Project Server 2007) we get "This
action may result in Actuals out of sync with.." message (the "Restrict
updates" option is
enabled). We go to tracking > sync with actuals, and save , but when we open
the
project again, we get the sync message again, before we even did anything at
all.
How can we sync back with actual from PWA..?
Also, Project wrongly spreaded hammock task's actual work, entered by user
in PWA, to something like 0.18h for every day of the next few weeks, so we
have changed the hammock task to fixed units and deselect effort driven, but
how do I recover the original (pre-spread) actual work values? can the
hammock task be the cause of the unfixable out-of sync state?
Thanks for any attempt to help..
Gil.