Hello,
I know I might not be building a plan in the most effective way. so
anyway...

I have created a plan. and on the resource usage view, I went in and
assigned out work. Week by week.
Is there any way to now make the start and stop fields sync up with the work
I have assigned?

thanks for any help
 
J

JulieS

Hi greg,

From your description, it sounds as though you may have gotten
things a bit muddled. When you assign resources to tasks the
calculated work on the assignment (visible in the Resource Usage
view) should line up with the start and finish dates of the task.
If there is only one resource assigned, contouring the work should
move the start and end dates. However, if more than one resource is
assigned or you're working with fixed duration tasks,or tasks with
constraints the task start date and finish date may not move.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project



"greg" wrote in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top