J
Jim
Hi folks,
I'm working with MSP2003 and PS2003. I have a project with afew tasks that have predecessor - successor relationships. They are F-S. Some have a lag, some have a lead time, some have neither. The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged. I've checked the calculation settings and it is set to recalculate automatically.
For example
Task 115 is a predecessor for task 117. T115's end date is June 28. T117's start date is June 30. If I change T115's end date to July 7, the startdate for T117 remains set to June 30.
Thanks for any insights.
Jim
I'm working with MSP2003 and PS2003. I have a project with afew tasks that have predecessor - successor relationships. They are F-S. Some have a lag, some have a lead time, some have neither. The issue I have is that when the finish date changes for a predecessor task, the start date for the successor remains unchanged. I've checked the calculation settings and it is set to recalculate automatically.
For example
Task 115 is a predecessor for task 117. T115's end date is June 28. T117's start date is June 30. If I change T115's end date to July 7, the startdate for T117 remains set to June 30.
Thanks for any insights.
Jim