M
michelle
This is my first project in Project Server. I loaded an existing project
using the recommended import method and republished assignments with the
update resource actuals box checked, so that I could get actuals already
recorded in the plan out to PWA. However, when I re-synch actuals
immediately after, some of the tasks I had updated to 100% complete change to
< 100%. This appears to happen randomly. What can I do to force tasks to
remain 100% complete, even after I re-synch actuals??
using the recommended import method and republished assignments with the
update resource actuals box checked, so that I could get actuals already
recorded in the plan out to PWA. However, when I re-synch actuals
immediately after, some of the tasks I had updated to 100% complete change to
< 100%. This appears to happen randomly. What can I do to force tasks to
remain 100% complete, even after I re-synch actuals??