Synching to Protected Actuals keeps changing % complete!

M

michelle

This is my first project in Project Server. I loaded an existing project
using the recommended import method and republished assignments with the
update resource actuals box checked, so that I could get actuals already
recorded in the plan out to PWA. However, when I re-synch actuals
immediately after, some of the tasks I had updated to 100% complete change to
< 100%. This appears to happen randomly. What can I do to force tasks to
remain 100% complete, even after I re-synch actuals??
 
M

michelle

Let me add...I've tried setting remaining work to 0, removing resources who
did not charge time, and removing all predecessors or constraints that might
be forcing an update. None of this works. Thanks!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top