Synchronization Problem

I

Itzik

Hi,
My resources report daily Actual Work and Remaining Work.
In several events I saw a variance between the remaining work in the e-mail
notification that was sent to me (the PM) and the remaing work in PWA
(Update view).
Any explanations?
Thanks,
Itzik
 
M

Marc Soester

Hi Itzik,

Your resources may have changed and updated the timesheet ( which will
trigger the email), and then have changed the value and only "saved" it
instead of update the timesheet. This would explain why.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top