I have an event which depends on completion of physical tasks, but It has a
series of reports that are du at t minus 2 wks, t minus 1 month, t minus 4
months, etc.
How can I schedule these so they reposnd as the principle event moves?
Ilink them but the reports just sit on the project start. If I make them
ALAP then they push the main event.
???