Activity 1.1: Assisting citizens to engage in effecting change
Increase Support to CMCs (demand side of governance)
Continue training/technical support to NGOs (CC tool, concept,
principles) P P P P P P Retreat 18-21 P P P P P POs (Supported by SGMOs)
NGOs provide training/technical support to CCs P P P P P P P P P P
P PNGOs (supported by POs)
Observe and feedback to CMCs in actions P P P P P P P P P P P
PNGOs (supported by POs)
Reflection session: CMCs' progress, concept, principles (tbc
NGOs/POs) P P PNGO Director (POs)
CMC tool kit formulation and implementation
Finalise layout and pictures P P Retreat 18-21
Pshum Ben 18-21 Soktha (working group)
Pre-testing took kit P P Soktha (working group)
Finalise tool kit (printing) P Soktha (working
group)
Implementing the tool kit (training with CMCs) P P P P P P
POs (SPOs)
Review and improve the kit (following quarter - Dec09)
Soktha (working group)
SF
how?
N° Main Activities Year 2009 Lead (Support)
Jul Aug Sep
Objective 1: Build sustainable horizontal and vertical links between
citizens, local government and national government (increase demand)
Activity 1.1: Assisting citizens to engage in effecting change
Increase Support to CMCs (demand side of governance)
Continue training/technical support to NGOs (CC tool, concept,
principles) P P P P P P Retreat 18-21 P P P P P POs (Supported by SGMOs)
NGOs provide training/technical support to CCs P P P P P P P P P P
P PNGOs (supported by POs)
Observe and feedback to CMCs in actions P P P P P P P P P P P
PNGOs (supported by POs)
Reflection session: CMCs' progress, concept, principles (tbc
NGOs/POs) P P PNGO Director (POs)
CMC tool kit formulation and implementation
Finalise layout and pictures P P Retreat 18-21
Pshum Ben 18-21 Soktha (working group)
Pre-testing took kit P P Soktha (working group)
Finalise tool kit (printing) P Soktha (working
group)
Implementing the tool kit (training with CMCs) P P P P P P
POs (SPOs)
Review and improve the kit (following quarter - Dec09)
Soktha (working group)