Taks Usage custom field - PS 2007

F

franklin

Apologies for cross-posting; noticed I had this in the Server section and not
the Developer section.

Is there no possible way of programmatically (VBA) referring to the custom
field values as per the task usage view? I attach a screen shot; trying to
reference either the "On Schedule" (Health) or "Value" (Text1) values (or any
similar custom values for that matter).

http://img365.imageshack.us/img365/3430/projectxd7.gif

These are NOT the same values as per the Resource Usage view, neither the
same as the Gantt view. These are in fact the same as the My Tasks view in
PWA.
 