B
blisspikle
Is there any way to have any of the tasks that I choose that are
complete, change the start date of another task?
Also, is there a way to assign several tasks under different
Milestones to update the % complete under another Milestone.
The company has overall tasks that they want to see complete like
Design, Build, etc. I have all of these tasks updated under the part
numbers we are building, and they each include Design, Build, etc. I
would like to be able to select tasks the way I have them organized
and fill out the information that they want to see. So if one part is
in the Design phase, and one has moved to Build, it will fill out
their information with Build has been started and give it a
percentage.
Thanks,
complete, change the start date of another task?
Also, is there a way to assign several tasks under different
Milestones to update the % complete under another Milestone.
The company has overall tasks that they want to see complete like
Design, Build, etc. I have all of these tasks updated under the part
numbers we are building, and they each include Design, Build, etc. I
would like to be able to select tasks the way I have them organized
and fill out the information that they want to see. So if one part is
in the Design phase, and one has moved to Build, it will fill out
their information with Build has been started and give it a
percentage.
Thanks,