I have one user that is receiving emails stating "the following tasks need
progress updates".......

None of her alerts are turned on. They've all been turned off for several
days but the emails continue to show up.

Seems like I'm missing something obvious here....anyone have any ideas?
 
M

mark.everett

Jody -

Alerts and Reminders come in two flavors. One is "Alert ME about MY
tasks etc" and the other is "Alert ME about MY RESOURCE'S tasks etc."
Mostly likely the project manager or, if you are using an RBS, a
resource manager, has the second option turned on.

Hope this helps.

Mark S. Everett | PMP
 