I have been experiencing exactly the same issue and unable to resolve this. Has a solution ever been found to this issue?
I am using MS Project 2007, Project Sever SP2.
Additionally, does anyone know how to stop the Project Owner being assigned a task by default if no resource is assigned to the task in the plan? We have a number of projects where a resource is not required to be defined. As a result the Plan owner in PWA is getting hundreds of tasks?
Thanks or any advice!
Nathan
MJ wrote:
Hi Seth,I tried the steps as you listed below, unfortunately it didn't solve
10-Aug-09
Hi Seth
I tried the steps as you listed below, unfortunately it did not solve th
issue we having. However, we found a way to workaround, change the statu
manager of certain amount of the tasks, so that we can update the tasks i
small amount
Interesting thing is after I updated the first 36 tasks, then I be able t
update the rest which is 178 tasks. So, maybe the max. is 200 tasks!
Thanks for the suggestions
:
Previous Posts In This Thread:
Task Approval Hangs
A user has 214 task updates from resources pending their approval. When the
go to the approvals.aspx page, the browser hangs
If they launch MS Project Professional, they see that there are 214 task
awaiting approval, however they experience the same hanging behavior insid
MS Project Pro 2007
Is this a bug? The behavior does not occur when there are a smaller numbe
of task updates pending approval
we are running SP2 on the server.
MJ,What will be very beneficial is to post some Event Logs here so we can
MJ
What will be very beneficial is to post some Event Logs here so we ca
peruse them and possibly help you. Just as a point of interest did yo
perhaps try it on another computer. We have found IE to be the problem i
situations like this
Regard
-
Andre Vente
Technical Consultan
UMT South Afric
MC
MCSE 200
MCITP Projec
MCTS Managing Project
MCTS Confiuring Project Serve
MCTS Charter Membe
MCTS MOS
MCITP Charter membe
:
There was a fix for more than 50 updates not working on the approvals page.
There was a fix for more than 50 updates not working on the approvals page
Have you applied SP2? I know this works in SP2 now (more than 50 updates)
Hope this help
-
Ray McCoppi
http://www.randsmanagement.co
SRS gantt chart
Project Server 2007 Archival Too
:
We had this issue crop up after our SP2 / Apr CU install and the fixfor users
We had this issue crop up after our SP2 / Apr CU install and the fi
for users that had this issue was
1. In any project plan, assign yourself a task and some work (thi
must be the PM that is having the issue
2. Save and Publish that pla
3. In PWA / =93My Tasks=94 enter time against this new tas
4. Submit your task for approval (assuming you are the approver fo
your tasks
5. Now go to =93Task Updates=94 (aka approvals) and you should be able t
see the Grid View again..
Let me know if this fixes your issue
Set
n the
d
mber
Hi Seth,I tried the steps as you listed below, unfortunately it didn't solve
Hi Seth
I tried the steps as you listed below, unfortunately it did not solve th
issue we having. However, we found a way to workaround, change the statu
manager of certain amount of the tasks, so that we can update the tasks i
small amount
Interesting thing is after I updated the first 36 tasks, then I be able t
update the rest which is 178 tasks. So, maybe the max. is 200 tasks!
Thanks for the suggestions
:
Submitted via EggHeadCafe - Software Developer Portal of Choice
Resize Images To Thumbnails in .NET
http://www.eggheadcafe.com/tutorial...e-1f791cbab9a9/resize-images-to-thumbnai.aspx