We are using the Project Server - Activities to allocate small project tasks
to engineers. This is working fine and a team of about 5 operation
controllers are creating activities with 2 or 3 tasks and allocating them.
When the Engineer updates his timesheet and task etc, he submits the Task
Update, and the operations controller who setup the activity gets the task
update for approval.
Is there anyway to set the system up for these users so that either they can
see all Task Updates for Approval in the Operations Controllers team, or that
they can view another users Approval list. We need this to cover holidays
etc.
Thanks
John
to engineers. This is working fine and a team of about 5 operation
controllers are creating activities with 2 or 3 tasks and allocating them.
When the Engineer updates his timesheet and task etc, he submits the Task
Update, and the operations controller who setup the activity gets the task
update for approval.
Is there anyway to set the system up for these users so that either they can
see all Task Updates for Approval in the Operations Controllers team, or that
they can view another users Approval list. We need this to cover holidays
etc.
Thanks
John