My tasks are all competed on time, why is the overall schedule showing behind?
J Jan De Messemaeker Jun 8, 2009 #2 Hi, Because not all your tasks are on time. You can send me the file if you want, I'l have a look. jandemesATprom-ade.be -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf
Hi, Because not all your tasks are on time. You can send me the file if you want, I'l have a look. jandemesATprom-ade.be -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf