Task-Assignment removed - flag existing?

S

Stefan Rauchegger

MSP 2003 Prof - ProjServer2003

I want to automate unattanded the publishing of new and changed
assignments.
I can manage wether work, duration has changed --> updateneeded = true
or task got new assignment, resulting in confirmed-property of
assignment beeing false.

BUT, where is the information logged, when the assignment of a task
was removed.
Project Client doesn't need to go to database (I've checked with
profiler). But I cannot find the property where this change is saved.

I've to check this, because PublishNew... brings up a popup, despite
showdialogs=false, when there is no need for Publishing :-(((

YHIA ASAP

Stefan
 