We are using MS Project Server 2007 and I am the system administrator, and as
such am responsible for setting up resources, new projects and also
performing the initial imports from .mpp files into Project Server. When I
import a project, I then edit the project properties in PWA and select the
real Project Owner from the drop down list (instead of myself). However,
where a project has local resources I find that all the tasks related to the
local resources are assigned to me (under My Tasks) - note that in the actual
project plan in Project Centre they show the actual local resources against
each task.
I assume that they show up on My Tasks in PWA as it needs a "known" PWA
resource to assign the work to for the purposes of notifications, etc. My
question is how do I reassign these to the new Project Manager so that they
no longer appear under My Tasks for myself? There is a Reassign button under
My Tasks, but wouldn't that also change the actual resource names in the
project plan as well ?
such am responsible for setting up resources, new projects and also
performing the initial imports from .mpp files into Project Server. When I
import a project, I then edit the project properties in PWA and select the
real Project Owner from the drop down list (instead of myself). However,
where a project has local resources I find that all the tasks related to the
local resources are assigned to me (under My Tasks) - note that in the actual
project plan in Project Centre they show the actual local resources against
each task.
I assume that they show up on My Tasks in PWA as it needs a "known" PWA
resource to assign the work to for the purposes of notifications, etc. My
question is how do I reassign these to the new Project Manager so that they
no longer appear under My Tasks for myself? There is a Reassign button under
My Tasks, but wouldn't that also change the actual resource names in the
project plan as well ?