D
Dave N.
I have 40 enterprise projects. I have 10 resources to assign to tasks. My
tasks are all fixed duration, not effort driven.
I have a 40 hour task with a duration of 60 days. I assigned 4 resources to
this task. Project divided the 40 hours among the 4 resources (10h each).
How can I allow up to 40 hours to be worked by any one of these 4 resources?
If one resource works 10 hours today, the task will be considered complete
for that resource and will not show up in PWA after they have worked 10 hours.
tasks are all fixed duration, not effort driven.
I have a 40 hour task with a duration of 60 days. I assigned 4 resources to
this task. Project divided the 40 hours among the 4 resources (10h each).
How can I allow up to 40 hours to be worked by any one of these 4 resources?
If one resource works 10 hours today, the task will be considered complete
for that resource and will not show up in PWA after they have worked 10 hours.