Task bar old location

C

c_robertson

I would like the ability to show a task's previous dates. Would this be
possible to display it as a faded taskbar? I know this is an exponential
ripple effect, but at least 1 step. This way when a project is delayed we can
displayed the previous schedule overlayed by the current schedule.
Maybe just the ability to overlay a complete schedule, but faded. All the
schedulers I know try to devise a way to do this.

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...a6b4-856dc2d73283&dg=microsoft.public.project
 
J

Jack Dahlgren MVP

From tools menu, tracking sub-menu, select save baseline.
From the views menu, select the tracking gantt.

This will show your original plan as the baseline and the current plan as
separate bars.

-Jack Dahlgren
 
C

c_robertson

Yes, the baseline shows where the task had been, but what were shooting for
here is showing the amount that was extended. We need the ability to show how
far the task was extended. The baseline shows how far a task was delayed, but
you don't know the amount of time it was extended.
 
J

JulieS

You could show the [Duration Variance] number next to the task bar
to show either positive or negative change to the task duration.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top