T
Tammy
Task baselining causes loss of BCWS information. I've
checked the status date to make sure it is today's date
and it is. This is a really bad issue. What's the point
of earned value if you can't rely on the calcs? Sure, you
could never ever baseline a new task - but not realistic
given our market. Any help would be appreciated. If I
can't do this comparison, is there any way to determine
what percentage complete you should be at the phase level
versus where you actually are (i.e. % complete versus the
status line denoting today's date on the gantt)?
Thanks,
Tammy
Subject: Re: baseline task loses project's BCWS
From: "Tammy" <[email protected]> Sent:
9/29/2003 12:15:44 PM
My status date is today's date.
checked the status date to make sure it is today's date
and it is. This is a really bad issue. What's the point
of earned value if you can't rely on the calcs? Sure, you
could never ever baseline a new task - but not realistic
given our market. Any help would be appreciated. If I
can't do this comparison, is there any way to determine
what percentage complete you should be at the phase level
versus where you actually are (i.e. % complete versus the
status line denoting today's date on the gantt)?
Thanks,
Tammy
Subject: Re: baseline task loses project's BCWS
From: "Tammy" <[email protected]> Sent:
9/29/2003 12:15:44 PM
My status date is today's date.
beginning of your project, the BCWS, which is-----Original Message-----
Hello Tammy,
Where is your Status date ? ( Project / Project information...)
If you move backward your Status date to the very
..calculed in connection with the status date, will go back to zero.
Hope this help,
Gérard Ducouret
"Tammy" <[email protected]> a écrit dans le message de [email protected]...
.