M
Meeting reminder
My customer has asked me to add a column as to actual finish date to my
project schedule After adding this task, I received some parts and added the
completion date to that task. I noticed my task which had a start and
completion date of 8 weeks now showed the same start and stop date and the
chart showed a milestone. Is this a structure problem or how do I retain the
start/stop dates and the progress bar?
thanks
project schedule After adding this task, I received some parts and added the
completion date to that task. I noticed my task which had a start and
completion date of 8 weeks now showed the same start and stop date and the
chart showed a milestone. Is this a structure problem or how do I retain the
start/stop dates and the progress bar?
thanks