D
DavidC
Hi, hope I can get some confirmation of how I believe the calendars for tasks
and resources operate together.
First I do understand that a task will first follow the calendar with the
greatest level of restriction of work time. Often this is the resource
calendar as many tasks are not necessarily constrained by time it is the
availablitity of a resource to carry out the task.
My project consists of activties which are calendar dependant and others
which are 24/7 tasks. Some tasks are carried out in the same location and
cannot be concurrent for H&S reasosn as well as simply cannot have two tasks
happening at the same time for lack of space. To identify if there is a
clash of tasks at a location I have set a resource labeled 'Location1' and
set that calendar to 24/7 since it is space used for both 24/7 tasks and
tasks which operate on a 'standard' calendar.
I have set a specific project calendar for the project NOT ther default
'standard'. However some tasks retain the 'none' default for the calendar.
When I apply the resource calendar to those tasks with a calendar 'none' it
changes start and finish dates. However when I set the task calendar to the
project calendar and again set the resource to the task it retains the
correct start and finish dates.
This leads me to the conclusion that by leaving the task calendar at 'none'
it allows the task to follow whichever calendar is available and if there are
no resources it uses the project calendar, but if a resource is applied the
dates use the resource calendar.
If my assumption is correct that helps in explaining to others why it is
important to always set a sepcific celndar to a task and not leave it at the
default 'none'.
I would appreciate feedback either positive and in agreement or negative to
explain where I have misunderstood the calculation of start and finish dates
and th interaction of task and resource calendars.
Many thanks
DavidC
and resources operate together.
First I do understand that a task will first follow the calendar with the
greatest level of restriction of work time. Often this is the resource
calendar as many tasks are not necessarily constrained by time it is the
availablitity of a resource to carry out the task.
My project consists of activties which are calendar dependant and others
which are 24/7 tasks. Some tasks are carried out in the same location and
cannot be concurrent for H&S reasosn as well as simply cannot have two tasks
happening at the same time for lack of space. To identify if there is a
clash of tasks at a location I have set a resource labeled 'Location1' and
set that calendar to 24/7 since it is space used for both 24/7 tasks and
tasks which operate on a 'standard' calendar.
I have set a specific project calendar for the project NOT ther default
'standard'. However some tasks retain the 'none' default for the calendar.
When I apply the resource calendar to those tasks with a calendar 'none' it
changes start and finish dates. However when I set the task calendar to the
project calendar and again set the resource to the task it retains the
correct start and finish dates.
This leads me to the conclusion that by leaving the task calendar at 'none'
it allows the task to follow whichever calendar is available and if there are
no resources it uses the project calendar, but if a resource is applied the
dates use the resource calendar.
If my assumption is correct that helps in explaining to others why it is
important to always set a sepcific celndar to a task and not leave it at the
default 'none'.
I would appreciate feedback either positive and in agreement or negative to
explain where I have misunderstood the calculation of start and finish dates
and th interaction of task and resource calendars.
Many thanks
DavidC