J
Jeff Michna
I have a project where certain tasks can only occur on
certain days of the week (Tue, Wed, Thur) while other
tasks are allowed to occur any day during the work week.
I've created a task calander that shows Tu,Wed, Th as non-
working, and have assigned the task to use this calendar.
However MS project shows the the task occuring on the non-
working days defined in the task calendar.
What am I doing wrong, and how can I fix it?
Thanks
certain days of the week (Tue, Wed, Thur) while other
tasks are allowed to occur any day during the work week.
I've created a task calander that shows Tu,Wed, Th as non-
working, and have assigned the task to use this calendar.
However MS project shows the the task occuring on the non-
working days defined in the task calendar.
What am I doing wrong, and how can I fix it?
Thanks