M
Maureen
When I set up and assign a task calendar that is different
to the default, Project still does not calculate the time
correctly. i.e. I have a 6X20 calendar for a 6 day 20
hour (2 - 10's) day, Project calculates it as 5 X 8 hour
days, which is the default. I have checked
the "Scheduling Ignores Resource Calendars" check box, but
it seems to make no difference. Has anyone else been able
to resolve this?
thanks for your help.
/m
to the default, Project still does not calculate the time
correctly. i.e. I have a 6X20 calendar for a 6 day 20
hour (2 - 10's) day, Project calculates it as 5 X 8 hour
days, which is the default. I have checked
the "Scheduling Ignores Resource Calendars" check box, but
it seems to make no difference. Has anyone else been able
to resolve this?
thanks for your help.
/m