B
bmorganh
I built a schedule using the Project Calender. I used fixed work method.
When I assigned a certain task to a special task calender that was 24-hours
per day the duration did not change. I would have expected for example a
48-hour fixed work activity to take 2 calendars to complete under the special
task calender. In summary when I assign calenders there is no change in
start and finish dates. What am I doing wrong?
When I assigned a certain task to a special task calender that was 24-hours
per day the duration did not change. I would have expected for example a
48-hour fixed work activity to take 2 calendars to complete under the special
task calender. In summary when I assign calenders there is no change in
start and finish dates. What am I doing wrong?