F
fefe78
Hi everybody
I have the following issue with Project Server 2003.
Once an activity is set to completed (setting the amount of work)
through PWA by a resource , when I go (as a manager) to accept the
changes and PWA opens Project Professional, the task activity %complete
is at 99%.
This behaviour is not the same for all tasks, as a matter of fact other
tasks reach correctly 100%.
I don't undestand why a few tasks behave differently from others.
I noticed that in 99% tasks the Actual Finish date is not set.
Is that a bug or a wrong task setting in project plan?
Thanks to everybody.
Bye
I have the following issue with Project Server 2003.
Once an activity is set to completed (setting the amount of work)
through PWA by a resource , when I go (as a manager) to accept the
changes and PWA opens Project Professional, the task activity %complete
is at 99%.
This behaviour is not the same for all tasks, as a matter of fact other
tasks reach correctly 100%.
I don't undestand why a few tasks behave differently from others.
I noticed that in 99% tasks the Actual Finish date is not set.
Is that a bug or a wrong task setting in project plan?
Thanks to everybody.
Bye