Task completed at 50%

S

Stefan Robert

Hi,

Let's say I have a 8 hours task. Is it possible to make the task 50%
complete even if my ressources did 10 hours on that task?

Thanks

Stefan
 
G

Gerard Ducouret

Hello Stefan,
Yes, ... if you estimate the Remaining Work at 10 hours !
NB : Don't enter the %Complete, but the actual Work and the remaining Work.
Project will calculate the %Work Complete.
Gérard Ducouret
 