Task completed not appearing

Y

yann

Dear all,
In PWA, i would like when a user has completed its task (100% completed)
that this one will not appear anymore on My Tasks.
How can I configure,,

Thanks
 
G

Gary L. Chefetz

yann:

They will appear in the all tasks view until you set the value in the
Publish field for the task to "No" and publish the project plan. Or, you
could look at a tool like our My Tasks Constant Filter web part:
https://projectdaddy.com/shopexd.asp?id=480
You can also get a free trial on the site.
 
B

Ben Howard [MVP]

Hi Yann,
I published some vba code on my blog on setting the task publish field = No
if the task is 100% complete.
 
Y

yann

Thanks Ben,

Your macro works it's good within Microsoft Project Plan.
Now I have to find a solution on how to do it automaticly within PWA.
Anyway, thank you again for your reply, it is very helpfull.
 