John said:
[QUOTE="Dave said:
Hi John,
Thank you for your answer. Here is the clarification. Even if task1
completes way after its original date, other wask that are supposed to be
linked (f-s) complete. The tasks are getting completed even if the
kick-off
meeting isn't complete. In other words, the work (technical stuff)
continues.
-jp
jp,
I think Jan pretty much covered it. It's interesting that you had a kick
off meeting that didn't "kick off" anything - the effort was already in
progress. In my view if a task doesn't have a successor then it is a
meaningless task and doesn't belong in the plan.
I can't see how that is generally true. It would be enough that it was
a deliverable for it to be in the Plan. For example, I may have a
complex software development which results in a complex network diagram.
The customer might also want a printer so they can print out their log
files. The printer is quite likely not to have a predecessor or
successor as it can be procured at any point during the project.
Dave,
ALL tasks must have a successor, otherwise they don't belong in the
plan. Everything in the plan must contribute to the project finish
milestone, otherwise, why is the task being done? Note, a deliverable is
not a task, it is a milestone.
A deliverable may be the final milestone or it may be an intermediate
milestone. A deliverable is an end item and it most likely will not
have a successor, (unless it is intermediate and drives more tasks), but
it must have a predecessor.
WIth regard to your example of procuring a printer. Is the printer
required in order to complete the project? If so, then the successor may
be the final milestone. If not, then the printer procurement does not
belong in the plan - it is an independent item.
John
Project MVP[/QUOTE]
I think that we're down to the definitions of terminology. It seemed to
me that in the context of the original question, you were saying that
the 'kick-off meeting' shouldn't have been in the plan because other
work proceeded before its completion (I agree it seems strange that the
work proceeded before its completion).
In my terminology, a deliverable is most definitely a task (because that
is the thing that has to be produced) and the delivery is the milestone
but that is semantics.
Ultimately we are saying the same thing.