R
RonnBlack
I have a project that was started some time ago.
Many tasks that were originally scheduled were never worked on and even
though they show 0% complete their expected completion times are in the past
because I have the project set to "start tasks as early as possible".
I want the project plan updated to show essentially the following "if I am
given full resources today what is estimated completion date".
I need it to recognize that I have entered status's as of a specific date
therefore, anything not complete as of the date statuses are updated is late
and adjust the schedule.
Is there any painless way to do this?
Many tasks that were originally scheduled were never worked on and even
though they show 0% complete their expected completion times are in the past
because I have the project set to "start tasks as early as possible".
I want the project plan updated to show essentially the following "if I am
given full resources today what is estimated completion date".
I need it to recognize that I have entered status's as of a specific date
therefore, anything not complete as of the date statuses are updated is late
and adjust the schedule.
Is there any painless way to do this?