Task Completion Dates in Past with 0% Complete

R

RonnBlack

I have a project that was started some time ago.
Many tasks that were originally scheduled were never worked on and even
though they show 0% complete their expected completion times are in the past
because I have the project set to "start tasks as early as possible".

I want the project plan updated to show essentially the following "if I am
given full resources today what is estimated completion date".

I need it to recognize that I have entered status's as of a specific date
therefore, anything not complete as of the date statuses are updated is late
and adjust the schedule.

Is there any painless way to do this?
 
M

Mike Glen

Hi Ronn,

Welcome to this Microsoft Project newsgroup :)

Yes - you need to update the project to the status date. Full details are
given in my series on Microsoft Project in the TechTrax ezine, particularly
towards the end of #26 on Progressing, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :) Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 