Task completion % on Project Server 2007 does not update correctly

  • Thread starter Deshwal - Magus India
  • Start date
D

Deshwal - Magus India

Hi,

I fill in my timesheets .. save the same ... go to task update ...import
timesheet data ...it updates task % complete .. to some say 30% .. now i open
the task update and change the remaining work to 20% more time and
recalculate .. the task complete % does not change ..

Timesheet .... work: 50 hrs, Actual work 40 hrs ...
Taks update ... import worksheet ..%complete: 80%... now if i change
remaining work to 20 hrs ... and recalculate .. %complete remains 80%..
 
W

wendy.li

The project manager shall accept the update,and re-distribute th
project to the project server, then the % will be updated on th
server.

Please try it
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top