% Task Completion

G

ggshankar

All my resources has updated the timesheet to 100% completion but i still the
task is 85% or 89% complete only. Is there a way to get the tasks to show
100% completion.

Thanks in advance.

Regards,
Shankar
 
R

RickD

I suggest you look at Remaining Work for the tasks that are complete but not
showing 100%. If the Remaining Work is > 0 set to zero and republish. Do not
mark the task 100% complete or you will be out of sync with timesheets.
 