M
martin de lange
Using P2003 & PWA
I am using hours logged per day on a task. As soon as the schedule (hours)
equal the (actual hours) then tasks are considered completed and gets a tick
next to the item. Is there any way that I can prevent the completion taking
place eg. for a monthly job catcher project. This task is amongs others
that do have determined hours tasks.
I put another custom column in to indicate a percentage of the work complete
to indicate to me when the task is complete but are there any other ways?
Any help would be much appreciated
I am using hours logged per day on a task. As soon as the schedule (hours)
equal the (actual hours) then tasks are considered completed and gets a tick
next to the item. Is there any way that I can prevent the completion taking
place eg. for a monthly job catcher project. This task is amongs others
that do have determined hours tasks.
I put another custom column in to indicate a percentage of the work complete
to indicate to me when the task is complete but are there any other ways?
Any help would be much appreciated