T
theintern
I have Start dates auto input to Project from Access. Then resources are
leveled and it looks great, with one task immediately following the next.
But if i change calendars, for example to one that has a longer workday, then
while the bars do get shorter, as desired, the second task doesn't stay
backed up to the first task, i.e. there is now a gap of downtime between the
two tasks. This is because the second task was given a task constraint of
SNET, which keeps it from moving any closer to the first task. I'd just get
rid of the task constraint, but if i change it to ASAP then the task
immediately flies to the left, to the Project start date. Is there any way
to keep tasks backed up one after the other while changing calendars? I hope
this is clear.
thanks
scott
leveled and it looks great, with one task immediately following the next.
But if i change calendars, for example to one that has a longer workday, then
while the bars do get shorter, as desired, the second task doesn't stay
backed up to the first task, i.e. there is now a gap of downtime between the
two tasks. This is because the second task was given a task constraint of
SNET, which keeps it from moving any closer to the first task. I'd just get
rid of the task constraint, but if i change it to ASAP then the task
immediately flies to the left, to the Project start date. Is there any way
to keep tasks backed up one after the other while changing calendars? I hope
this is clear.
thanks
scott