A
aceofclubs37
i have a problem with a task cost. i have a programmer quoting me for a
portion of a project, however there are tasks throughout the project related
to the quote.
Curently when i try my different costing options it takes the quote value
and applies it against each instance of a task related to the quote. I have
test "cost", "work", and "material" type costing however i cannot configure
that to work.
i understand the summary task cost concept, however that is now how my
project is setup. these programmer tasks are a part of other summary tasks.
So what i am trying to obtain is one cost from this programmer, related to
multiple task throughout the project.
Thank you in advance for any suggestions.
portion of a project, however there are tasks throughout the project related
to the quote.
Curently when i try my different costing options it takes the quote value
and applies it against each instance of a task related to the quote. I have
test "cost", "work", and "material" type costing however i cannot configure
that to work.
i understand the summary task cost concept, however that is now how my
project is setup. these programmer tasks are a part of other summary tasks.
So what i am trying to obtain is one cost from this programmer, related to
multiple task throughout the project.
Thank you in advance for any suggestions.