Task creation problems in PWA

D

danielp37

Resources can add new tasks to existing projects for themselves in the
"My Tasks" page on PWA but those tasks don't seem to be added to the
project even after the project manager approves the projects. In
fact, if the project manager syncs the project with Project
Professional 2007, the tasks get deleted.

What are we doing wrong and how do we fix it so that resources can add
tasks and after those tasks get approved by the PM, they get added to
the Project so that they still show up on Project Professional?

Thanks,

Dan
 
M

Mike Glen

Hi Dan,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top