D
danielp37
Resources can add new tasks to existing projects for themselves in the
"My Tasks" page on PWA but those tasks don't seem to be added to the
project even after the project manager approves the projects. In
fact, if the project manager syncs the project with Project
Professional 2007, the tasks get deleted.
What are we doing wrong and how do we fix it so that resources can add
tasks and after those tasks get approved by the PM, they get added to
the Project so that they still show up on Project Professional?
Thanks,
Dan
"My Tasks" page on PWA but those tasks don't seem to be added to the
project even after the project manager approves the projects. In
fact, if the project manager syncs the project with Project
Professional 2007, the tasks get deleted.
What are we doing wrong and how do we fix it so that resources can add
tasks and after those tasks get approved by the PM, they get added to
the Project so that they still show up on Project Professional?
Thanks,
Dan