P
PhilosophersSage
I am using MSP2003 and have read quite a bit about project since I first
started using it just over a month ago but have not found my answer. We have
five different groups that work production and at times one or more may me
working abnormal hours to maintain schedule is there a way to set working
days/hours for a specific task or group of tasks. I have seen the ability to
end a task on a non-working day, but not begin or work through a weekend.
started using it just over a month ago but have not found my answer. We have
five different groups that work production and at times one or more may me
working abnormal hours to maintain schedule is there a way to set working
days/hours for a specific task or group of tasks. I have seen the ability to
end a task on a non-working day, but not begin or work through a weekend.