P
Prash
Hi,
We are trying to find out when a team member finishes a task early, how can
they report the date changes to PM. for example, if a task is supposed to
take 10 days and on 8th day the task assignee reports 100% completion on PWA,
can the system move the end date 2 days early to reflect that task is
complete?
We noticed that this does not happen in PWA and may be by design. Do we need
to tell the team members that if they have to report task finished early or
late, they need to report the progress in % and the changed date in finish
date too on PWA? thanks ..
We are trying to find out when a team member finishes a task early, how can
they report the date changes to PM. for example, if a task is supposed to
take 10 days and on 8th day the task assignee reports 100% completion on PWA,
can the system move the end date 2 days early to reflect that task is
complete?
We noticed that this does not happen in PWA and may be by design. Do we need
to tell the team members that if they have to report task finished early or
late, they need to report the progress in % and the changed date in finish
date too on PWA? thanks ..