R
Rex
Our business has a due date for various client projects with tasks that need
to be completed x amount of days before this due date and some that need to
be completed y amount of days after this due date.
For example:
Task 1 needs to be done 7 days before the the due date (-7 days).
Task 2 needs to be done 3 days before the due date (-3 days).
The due date (0 days).
Task 3 needs to be done 30 days after the due date (+30 days).
Task 4 needs to be done 90 days after the due date (+90 days).
The due date is what drives all other task dates.
Other than making Task 4 the end date and backing up the other tasks
accordinly (including the due date), I'm wondering if there's a way to do the
above in Project 2002.
I've done a fair amount of research and tested different ways to try and
accomplish this but am admittedly not a Project power user and don't have the
time right now to become one so I'm posting this to the power users.
Thank you for your help and understanding.
to be completed x amount of days before this due date and some that need to
be completed y amount of days after this due date.
For example:
Task 1 needs to be done 7 days before the the due date (-7 days).
Task 2 needs to be done 3 days before the due date (-3 days).
The due date (0 days).
Task 3 needs to be done 30 days after the due date (+30 days).
Task 4 needs to be done 90 days after the due date (+90 days).
The due date is what drives all other task dates.
Other than making Task 4 the end date and backing up the other tasks
accordinly (including the due date), I'm wondering if there's a way to do the
above in Project 2002.
I've done a fair amount of research and tested different ways to try and
accomplish this but am admittedly not a Project power user and don't have the
time right now to become one so I'm posting this to the power users.
Thank you for your help and understanding.