Using MS Project 2002/Windows XP.
I have a project plan setup and need to change the start date for the
project. All the tasks are linked with Finish-to-Start constraints,
with the task constraints set to As Soon As Possible.
There is one milestone task which is not connected to any other tasks.
If I change the project start date (Project>Project Information) there
is no change to the timeline.
If I change the start date of the first task, it shifts along the
timeline, but all the other tasks stay where they are.
Can anyone help?
Regards
James.
I have a project plan setup and need to change the start date for the
project. All the tasks are linked with Finish-to-Start constraints,
with the task constraints set to As Soon As Possible.
There is one milestone task which is not connected to any other tasks.
If I change the project start date (Project>Project Information) there
is no change to the timeline.
If I change the start date of the first task, it shifts along the
timeline, but all the other tasks stay where they are.
Can anyone help?
Regards
James.