P
Phillip
Has anyone ever seen the dates in a notification email for a task, showing
different dates than in the schedule?
I have a situation where the start date in the notification email (Feb. 15)
is 7 days later for the task that is in the actual schedule (Feb. 8); the
finish dates are the same (March 19)...
Thanks.
different dates than in the schedule?
I have a situation where the start date in the notification email (Feb. 15)
is 7 days later for the task that is in the actual schedule (Feb. 8); the
finish dates are the same (March 19)...
Thanks.