J
jp
Hi,
I have TaskZ that was supposed to start on 7/10/09. However, due to other
projects the task has been delayed a few days. Then they were supposed to
work on it on 7/13/09 and then they told me it had to be put on hold until
7/17/09. Then they notified me that they haven't started working on it
because the resource was sick and the new potential start is 7/24/09.
Question: How should I handle the update for this task?
Thanks
-jaime
I have TaskZ that was supposed to start on 7/10/09. However, due to other
projects the task has been delayed a few days. Then they were supposed to
work on it on 7/13/09 and then they told me it had to be put on hold until
7/17/09. Then they notified me that they haven't started working on it
because the resource was sick and the new potential start is 7/24/09.
Question: How should I handle the update for this task?
Thanks
-jaime