N
Natasha
I currently have a project plan, due to company policies, where all
tasks are set to begin as soon as possible and have a predecessor w/no
contraints. My problem is some of my tasks still have contraints
(Start no Earlier) now matter how many times I reset these defaults.
When I reopen the plan the contraints are back. My question is do
dependencies cause contraints? How will I know if that is the case?
Thank you for all your help
tasks are set to begin as soon as possible and have a predecessor w/no
contraints. My problem is some of my tasks still have contraints
(Start no Earlier) now matter how many times I reset these defaults.
When I reopen the plan the contraints are back. My question is do
dependencies cause contraints? How will I know if that is the case?
Thank you for all your help