Task dependencies

K

Kath Pittelkow

I would like to link multiple tasks to TASK A where the TASK A is forecasted to start 2 months before the earliest predecessor task. TASK A is used as a reminder for a team to notify another team of something. However, during early planning, we are unsure which of the multiple predecessor tasks will start first. Is this possible?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top