Hi All,
I have a project where my procurement depends on the usage
of a material in the future e.g. I have to procure 4 weeks
before the materials is required.
In this respect, if the material usage is put back 4
weeks, then I want the procurement to also move 4 weeks
(retaining the 4 weeks lead-time). However, because the
procurement tasks occurs before it remains in the same
timescale and the procurement lead-time becomes 8 weeks
(does this make sense?)
If so, could any of the users in the NG assist me to
create the link to ensure my predecessor moves according
to my successor task?
TIA - H
I have a project where my procurement depends on the usage
of a material in the future e.g. I have to procure 4 weeks
before the materials is required.
In this respect, if the material usage is put back 4
weeks, then I want the procurement to also move 4 weeks
(retaining the 4 weeks lead-time). However, because the
procurement tasks occurs before it remains in the same
timescale and the procurement lead-time becomes 8 weeks
(does this make sense?)
If so, could any of the users in the NG assist me to
create the link to ensure my predecessor moves according
to my successor task?
TIA - H