Task dependency problem FS to FF

S

Stunt

I have a problem setting up task dependencies:

I have Task 1 and Task 2 setup in a normal FS behaviour e.g. Task2
cannot start before Task 1 is finished.
This is a simplified example, and in my case Task 1 and 2 consist of
many subcases and all dates / durations are variable.

Now i want to create a Task 3 with start date (task 1 finish) and
finish date (task 2 Finish), meaning it cannot start before T1 finishes
and cannot end before T2 finishes.

It doesnt work if i link like this 1FS;2FF

How can i setup a Task 3 with variable duration from T1 finish to T2
finish?

Thanks!
Stunt
 