S
Stunt
I have a problem setting up task dependencies:
I have Task 1 and Task 2 setup in a normal FS behaviour e.g. Task2
cannot start before Task 1 is finished.
This is a simplified example, and in my case Task 1 and 2 consist of
many subcases and all dates / durations are variable.
Now i want to create a Task 3 with start date (task 1 finish) and
finish date (task 2 Finish), meaning it cannot start before T1 finishes
and cannot end before T2 finishes.
It doesnt work if i link like this 1FS;2FF
How can i setup a Task 3 with variable duration from T1 finish to T2
finish?
Thanks!
Stunt
I have Task 1 and Task 2 setup in a normal FS behaviour e.g. Task2
cannot start before Task 1 is finished.
This is a simplified example, and in my case Task 1 and 2 consist of
many subcases and all dates / durations are variable.
Now i want to create a Task 3 with start date (task 1 finish) and
finish date (task 2 Finish), meaning it cannot start before T1 finishes
and cannot end before T2 finishes.
It doesnt work if i link like this 1FS;2FF
How can i setup a Task 3 with variable duration from T1 finish to T2
finish?
Thanks!
Stunt