B
Bert288gto
Something odd happened in Project. Bug? or something I did?
Always, if you want to have task 6 have a FS relationship with task 5 one
would put 5 in the predecessor column of row 6. That is Project 101.
Well, oddly my schedule did a switcheroo. In order to have a FS
relationship between tasks 5 and 6, I now need to put 6 in the predecessor
column of row 5.
Always, if you want to have task 6 have a FS relationship with task 5 one
would put 5 in the predecessor column of row 6. That is Project 101.
Well, oddly my schedule did a switcheroo. In order to have a FS
relationship between tasks 5 and 6, I now need to put 6 in the predecessor
column of row 5.