Not exactly - suppose I have two tasks & the initial
planning is: one starting April 1, the other one April 3.
I now have a third task, that starts whatever is the
earliest starting date of the two other tasks. In the
initial planning this would be April 1, but think of a
project with many parallel tasks (>20), quite frequent
changes of starting dates, and very dense time-intervals
between the different tasks.
What I want to avoid is the reprogramming of the task-
dependencies, since my real-world example has many (really
a lot!) parallel tasks; and one task starting whenever one
of the parallel tasks starts. As a simplification think of
a scenario "first customer in" triggers "publish success
story in the internet" - but on a very time-compressed
schedule, so you do not want to fiddle around with
updating your task-dependencies....
Again my question: any idea how you can handle this (I
think this cannot be covered by FF, FS, SF, SS
relationships)?
Thanks in advance,
Klaus